Three kinds of CAMA permits
North Carolina’s Coastal Area Management Act (CAMA) is run by the Division of Coastal Management (DCM). Docks, piers, boat lifts, and bulkheads are built in or over coastal waters and shorelines, so they usually need one of three kinds of permits 1:
- General permits cover routine projects that usually pose little or no threat to the environment. DCM staff issue them on site, and they are available through DCM’s online permitting system 1. Many residential docks, lifts, and bulkheads that meet the standard conditions use this route.
- Major permits apply to projects that need other state or federal permits, cover more than 20 acres, or involve more than 60,000 square feet of construction. Ten state and four federal agencies review them before DCM decides 1.
- Minor permits cover projects, such as single-family houses, that need neither a major nor a general permit. Local governments under contract with DCM issue them, generally within 25 days of a complete application 1.
A project that does not fit the general permit’s conditions does not simply get approved with an exception. It moves to a different, more involved review, if it can be permitted at all.
How a general permit for a dock or pier works
The general permit for piers and docking facilities is set out in 15A NCAC 07H, Section .1200. Its approval rule lays out the steps 2:
- Contact DCM with the site location, project dimensions, and your name and address 2.
- Notify your neighbors. Either get a signed statement from the adjacent riparian owners saying they do not object, or notify them by certified mail. Neighbors have 10 days from receipt to send written comments, and no response is treated as no objection 2.
- Meet on site. No work may start until an on-site meeting with a DCM representative 2.
- Build within 120 days. Construction must be finished within 120 days of the permit being issued, or the authorization expires 2.
- Get approval for changes. Any modification or addition needs prior DCM approval 2.
If neighbor comments raise real concerns, DCM can require a major permit application instead 2.
Key limits for docks, piers, and boat lifts
The specific conditions in 15A NCAC 07H .1205 decide what fits under the general permit 3. The ones that most often shape a Brunswick County project are:
- Riparian setback. Every part of the pier and dock must be at least 15 feet from the adjacent property lines extended into the water, unless the neighbor waives it in writing 3.
- Length. Up to 400 feet waterward of normal high water, never more than one-quarter of the width of the water body, and not past the established pier length along the shoreline for similar use (with some exceptions for piers of 100 feet or less) 3.
- Width and height. Piers no wider than six feet, elevated at least three feet above any coastal wetland 3.
- Boat lifts. The area enclosed by a lift may not exceed 400 square feet 3.
- Docks and platforms. No single component larger than 400 square feet, and total shaded area for docks (not counting the pier) of 8 square feet per foot of shoreline, up to 800 square feet 3.
- Boats and stories. Docking space for no more than two boats, and single-story only, though it may be roofed 3.
- Floating docks over sensitive bottoms. Over shellfish beds, submerged grasses, or primary nursery areas, at least 18 inches between the float bottom and the bottom of the water at normal low water 3.
Neighbors can share a pier along their common property line, with docking space for up to four boats, under the same rule 3.
Key limits for bulkheads and seawalls
Bulkheads have their own general permit in Section .1100. Under its specific conditions 4:
- On shorelines without wetland plants, a new bulkhead may sit no more than five feet waterward of normal high water at any point 4.
- A replacement bulkhead generally may move no more than two feet waterward of the existing wall, or up to five feet to tie into a similar wall next door 4.
- Where wetland vegetation is present, all construction must stay landward of it 4.
- The permit covers up to 500 feet of shoreline, and the wall must be built before backfilling, with fill from an upland source 4.
Repairs, replacement, and who to call
Repair or replacement? Under state rules, repairing storm or age damage is not development and does not need a CAMA permit, but replacement does 5. Work on a fixed dock, pier, or boat lift counts as replacement if more than 50 percent of the framing and structural parts must be rebuilt, or if the structure gets bigger in any dimension 5. For floating docks, the test is more than 50 percent of the square footage; for bulkheads, more than 50 percent of the length 5. A boat lift that stands on its own is judged separately from the dock beside it 5.
Who to call. Brunswick County is served by DCM’s Wilmington District Office, which covers Brunswick, New Hanover, and Pender counties. The office is at 127 Cardinal Drive Ext., Wilmington, NC 28405, and the main line is 910-796-7215 6. Call before you finalize a design. Staff can tell you which permit applies and whether your site has wetlands, shellfish areas, or other features that change the rules.
Federal rules. Along federally maintained channels, the state rule also requires docks to meet U.S. Army Corps of Engineers requirements under Section 10 of the Rivers and Harbors Act 3.
S&F Marine Construction builds docks, piers, lifts, and seawalls, but permit decisions belong to DCM, and no contractor can guarantee an approval or a timeline. When you are ready to talk through a project, a free estimate is a good time to bring your survey and any questions about how the rules apply to your lot.
Common questions
Do I need a CAMA permit for a new dock in Brunswick County?
Almost always. Many residential docks qualify for a general permit if they meet the state’s conditions on setbacks, size, and the number of boats. Confirm with the DCM Wilmington District Office at 910-796-7215.
What is the riparian setback for a dock in North Carolina?
Under the general permit, every part of the pier and dock must stay at least 15 feet from the neighboring property lines extended into the water, unless the neighbor waives the setback in writing.
Does a boat lift need its own permit?
Boat lifts are covered by the same general permit as piers and docks. The area enclosed by a lift may not exceed 400 square feet, and the setback and other conditions still apply.
Do I need a permit to repair my dock or seawall?
Repair is not considered development under state rules. It becomes replacement, which needs a permit, if more than half of a fixed dock’s structure, a floating dock’s area, or a bulkhead’s length must be rebuilt, or if the structure is enlarged.
Sources
- Types of Permits (CAMA major, general, and minor), NC DEQ, Division of Coastal Management.
- 15A NCAC 07H .1202 — Approval Procedures (General Permit for Piers and Docking Facilities), NC Administrative Code (Office of Administrative Hearings).
- 15A NCAC 07H .1205 — Specific Conditions (Piers, Docking Facilities, and Boat Lifts), NC Administrative Code (Office of Administrative Hearings).
- 15A NCAC 07H .1105 — Specific Conditions (Bulkheads and Riprap Revetments), NC Administrative Code (Office of Administrative Hearings).
- 15A NCAC 07J .0210 — Replacement of Existing Structures, NC Administrative Code (Office of Administrative Hearings).
- DCM Offices & Program Areas (Wilmington District Office), NC DEQ, Division of Coastal Management.